An Aug. 1, 2019 photo shows crews working to remove wind turbines from Helder Park in Zeeland. HOLLAND TOWNSHIP, Mich. (WOOD) — Wind turbines in Helder Park in Holland Township are being torn down.

The city of Zeeland built the turbines in 2009 in an effort to use more sustainable energy.

The turbines were placed outside the city limits due to zoning issues. The park was chosen by engineers who believed it was the best place to generate wind.

It cost the city about $457,000. Right after the turbines went up, the city says things went downhill.

“Shortly after that, the manufacturer of those units went out of business,” said Andrew Boatright with the city’s public works department.

Boatright says it made finding parts to repair the turbines nearly impossible and incredibly costly.

“The maintenance issues were a big problem. In 2014, there was a significant period of no operation,” Boatright added. “It just got to a point where they became a maintenance concern and a safety hazard.” .... continues.

" If the American People ever allow private banks to control the issue of currency, first by inflation and then by deflation, the banks and corporations that will grow up around them, will deprive the people of their property until their children will wake up homeless on the continent their fathers conquered... "

--Thomas Jefferson

HatCountry.com Cowgirl Hats!

We could use your help!

Your contribution is appreciated, if only a couple of bucks, the cost of countering the liberal media is arduous and costly.

SiteLock

HatCountry.com Cowgirl Hats!